Sterlite Power acquires Khavda Phase-IV (7GW): Part C project

  • Industry News
  • Sep 02,24
The Phase IV, Part C project includes the construction of various major integral components – 1) a 258 km, 765kV transmission corridor connecting South Olpad (GIS) S/s to Boisar-II (GIS) S/s., 2) construction of a 6000 MVA, 765/400/220kV GIS Substation at Boisar-II. 3)
Sterlite Power acquires Khavda Phase-IV (7GW): Part C project

Sterlite Power, a leading power transmission developer and global products and services provider, has secured Khavda Phase-IV (7GW): Part C project to develop the transmission system for evacuating power from the potential renewable energy zone in the Khavda region. This order win marks Sterlite Power’s second venture into green energy transmission projects in the state of Gujarat and is the company's fifth green energy evacuation project overall. The 30 GW capacity hybrid (solar and wind) renewable energy park at Khavda, located along the Indo-Pak border, was inaugurated by the Hon’ble Prime Minister of India in December 2020. The Phase-IV transmission scheme aims to evacuate an additional 7 GW of renewable energy from this park with a scheduled COD of 24 months from SPV acquisition.

Sterlite Power announced the acquisition of Khavda IV C Power Transmission Limited, a Special Purpose Vehicle (SPV) from REC Power Development and Consultancy Limited, a wholly-owned subsidiary of REC Limited. This project is a significant milestone in advancing India’s renewable energy infrastructure and aligns with the government’s vision of installing 500 GW of renewable energy capacity by 2030.

The Phase IV, Part C project includes the construction of various major integral components – 1) a 258 km, 765kV transmission corridor connecting South Olpad (GIS) S/s to Boisar-II (GIS) S/s., 2) construction of a 6000 MVA, 765/400/220kV GIS Substation at Boisar-II. 3) construction of two LILO lines, covering approximately 162 km and terminating at Boisar-II, 4) construction of a 21 km, 400kV transmission corridor connecting from Boisar-II (GIS) S/s to Velgaon (GIS) S/s. The project also includes the implementation of STATCOM systems at Boisar-II and Navsari substations.

Pratik Agarwal, Managing Director, Sterlite Power said, “This project is a vital part of our commitment to reducing the carbon footprint and enhancing the green energy transmission infrastructure in India. Our endeavour is to consistently innovate and build solutions that bolster the country's green energy ambitions.”

This project will evacuate green power from Gujarat, providing a critical link for power disbursal from the Khavda area to South Olpad, Boisar, and further to the Pune area. The development of this infrastructure will strengthen the energy infrastructure within Maharashtra and meet the energy needs of the state, particularly benefiting the load centres in the Mumbai Metropolitan Region (MMR) and Pune.
REC Power Development and Consultancy Ltd. coordinated the bid process for this project, with major players like Sterlite Power, PGCIL, and Adani Transmission participating in the bid.

Related Stories

Electrical & Electronics
Juniper Green Adds 64 MWp Renewable Capacity across Gujarat and Maharashtra

Juniper Green Adds 64 MWp Renewable Capacity across Gujarat and Maharashtra

Juniper Green Energy commissions ~64 MWp, completing wind and solar projects months ahead of schedule, underscoring its strong execution and clean energy focus.

Read more
Heating & Cooling Equipment
Ingersoll Rand Opens New Manufacturing Facility in Sanand, Gujarat

Ingersoll Rand Opens New Manufacturing Facility in Sanand, Gujarat

Ingersoll Rand’s new manufacturing facility in Sanand is one of its largest investments in India, and is set to begin production by the fourth quarter of fiscal year 2025.

Read more
Other Industrial Products
Swan Defence signs Rs 42.50 bn MoU with GMB to boost shipbuilding

Swan Defence signs Rs 42.50 bn MoU with GMB to boost shipbuilding

Swan Defence and GMB will expand shipyard capacity, build a 200-acre cluster, and set up a maritime Centre of Excellence.

Read more

Related Products

Integrated Electric Gripper S Series

ELECTRICAL & ELECTRONIC EQUIPMENT

IBK Engineers Pvt Ltd offers a wide range of integrated electric gripper S series.

Read more

Request a Quote

Geared Electric Motors

ELECTRICAL & ELECTRONIC EQUIPMENT

Delco Fans Pvt Ltd offers single phase capacitor run and three phase geared Instrument motors, totally enclosed face/foot mounted.

Read more

Request a Quote

Hi There!

Now get regular updates from IPF Magazine on WhatsApp!

Click on link below, message us with a simple hi, and SAVE our number

You will have subscribed to our Industrial News on Whatsapp! Enjoy

+91 84228 74016