Slow progress hampers development of electronic manufacturing at Tuem

  • Industry News
  • Aug 05,24
The commissioning of a 33/11kV substation, built at a cost of Rs 428 million, is significantly delayed.
Slow progress hampers development of electronic manufacturing at Tuem

The development of the Tuem Electronics System Design and Manufacturing (ESDM) Park is moving at a sluggish pace, with basic infrastructure still inadequate. Despite the allocation of plots to nine companies, progress has been slow, with another 10 applications under review. The primary reason for the delay is the lack of essential amenities such as power and water, causing companies to hesitate in setting up their manufacturing facilities.

The commissioning of a 33/11kV substation, built at a cost of Rs 428 million, is significantly delayed. The deadline for the substation's completion, after two extensions, was set for April 13. However, only 95% of the work has been completed so far. Additionally, the incomplete water infrastructure at Tuem ESDM Park remains a significant concern. While a 1,200 cubic metre sump and water supply pipelines have been completed, the 650 cubic metre overhead reservoir and pumping system are still under construction. As a temporary solution, the government has proposed utilizing the 1,200 cubic metre sump to supply water.

"To date, nine plots have been allotted. However, the industries/companies have yet to begin setting up their units. No applications for electricity connections have been received from plot owners," said the Department of Information Technology, Electronics, and Communications.

The department has allocated plots to Kenkre Generators Sales and Service, Mega Electricals, Samanvii Digimedia Art and Solutions, Sol Innocab, Prestine Engineering Services, Natekar Industries, Salvonic Technologies, Zen Technologies and Thinvent Technologies. Four applications were rejected. Aequs, a leading aerospace precision engineering firm, had expressed interest in setting up a manufacturing unit at Tuem ESDM Park with an investment of Rs 5 billion but shifted its focus to other states due to the delays.

To attract more investments, the department is formulating a policy for electronics system design and manufacturing. The slow pace of development is evident, as the foundation stone for the Tuem cluster was laid in June 2015 by then Chief Minister Laxmikant Parsekar. The current expectation is for the Tuem park to be ready by October 2024.
(Source: TOI)

Related Stories

Policy Regulation
Slow progress hampers development of electronic manufacturing at Tuem

Slow progress hampers development of electronic manufacturing at Tuem

The commissioning of a 33/11kV substation, built at a cost of Rs 428 million, is significantly delayed.

Read more
Electrical & Electronics
 Lava to detach manufacturing arm into independent entity

Lava to detach manufacturing arm into independent entity

Lava, which has struggled to meet its PLI targets since the scheme's inception in 2020-21, is optimistic about a turnaround with the new incentive package for component production.

Read more
Smart Manufacturing
Tata official: Talent deficit hinders India's manufacturing goals

Tata official: Talent deficit hinders India's manufacturing goals

He also said that the manufacture of mobile phones in India is just assembly with not enough value addition

Read more

Related Products

Hi There!

Now get regular updates from IPF Magazine on WhatsApp!

Click on link below, message us with a simple hi, and SAVE our number

You will have subscribed to our Industrial News on Whatsapp! Enjoy

+91 84228 74016

Reach out to us

Call us at +91 8108603000 or

Schedule a Call Back