Railways to revise Rs 310 billion wagon procurement plan after MI contract fail

  • Industry News
  • Jul 01,24
The wagons - which are used for transporting crucial commodities such coal and iron ore on the rail network - were to be supplied at Rs 3.19-3.63 million per unit depending on the specifications issued by the railways.
Railways to revise Rs 310 billion wagon procurement plan after MI contract fail

The Indian Railways has had to revise its plan for procuring wagons worth Rs 310 billion after supplier Modern Industries failed to fulfil its contracted obligations, officials stated.

In July 2022, the government awarded contracts for 79,800 wagons to seven suppliers, in what was the largest such procurement initiative by volume, aimed at boosting the existing fleet of 300,000 wagons on the Indian Railways network. The successful bidders included Titagarh Wagons, Texmaco Rail and Engineering, Hindustan Engineering Industries, Commercial Engineer and Body Builders (now Jupiter Wagons), Oriental Foundry, Besco, and Modern Industries.

Modern Industries, initially contracted to supply 9,242 wagons for Rs 37.76 billion, faced challenges related to prolonged labour unrest that hindered production. Consequently, the order was downsized last month under force majeure conditions to 3,151 wagons amounting to Rs 12.87 billion, as per a Railway Board directive. The company has delivered only 71 wagons to date.

The railways intend to compensate for this shortfall by increasing orders with other wagon suppliers. For instance, in February this year, the procurement from Hindustan Engineering Industries was expanded by 343 wagons, bringing the total order with them to 7,506 units.

Force majeure, a contractual provision relieving parties from obligations due to unforeseen circumstances, was invoked by Modern Industries due to labour disruptions affecting production. Queries sent to Modern Industries by ET remained unanswered at the time of publication.

Officials emphasised that the financial adjustments due to the scaled-down order had no adverse impact on either party.

 (Source: Economic Times)

Related Stories

Railways
Railways to revise Rs 310 billion wagon procurement plan after MI contract fail

Railways to revise Rs 310 billion wagon procurement plan after MI contract fail

The wagons - which are used for transporting crucial commodities such coal and iron ore on the rail network - were to be supplied at Rs 3.19-3.63 million per unit depending on the specifications iss..

Read more
Railways
Titagarh Rail Systems to develop driverless metro trains

Titagarh Rail Systems to develop driverless metro trains

A critical supplier to Indian Railways, it currently produces 1,000 wagons a month.

Read more

Related Products

Hi There!

Now get regular updates from IPF Magazine on WhatsApp!

Click on link below, message us with a simple hi, and SAVE our number

You will have subscribed to our Industrial News on Whatsapp! Enjoy

+91 84228 74016

Reach out to us

Call us at +91 8108603000 or

Schedule a Call Back